Why Accurate DC Cable Sizing Matters in Utility-Scale Solar

BTR Enerji Engineering Team · Published: 29 September 2026 · 4 min read

DC cabling looks like a small line in a PV budget, but the wrong cross-section or an unrealistic cable quantity sets both the capital cost and an energy loss repeated every day for 25–30 years. This article explains how string cables are sized and how the layout changes the cable quantity.

Three criteria for DC cable selection

The voltage-drop formula

The DC voltage drop of one string, in percent:

ΔU% = 2 × L × I × R′ / U × 100

L is the one-way cable length (m), I the string current (A), R′ the resistance per metre at operating temperature (Ω/m) and U the string voltage (V). The factor 2 accounts for the outgoing and return conductors. Copper resistance rises with temperature (about 0.39%/°C): a 6 mm² solar cable with roughly 3.39 Ω/km at 20 °C exceeds 4 Ω/km at 70 °C.

Worked example

A 28-module string operates at 41.7 V × 28 ≈ 1,168 V and 13.3 A on a 6 mm² cable at 70 °C (≈ 4.06 Ω/km):

One-way distanceVoltage dropComment
60 m≈ 0.55%Inverter next to its table group
150 m≈ 1.39%At the design target
300 m≈ 2.8%Change the cross-section or the topology

The annual energy loss is lower than this full-power figure, because the plant runs at part load most of the time and the loss falls with the square of the current. Long string cables still add up to a significant loss over the project lifetime.

Tracker or fixed-tilt: which is more profitable on your site?
Pick your location and draw your land on the map. Get hourly-weather-based yield, a tracker vs fixed-tilt comparison, a bill of materials and the payback period, free of charge.
Free Solar Tracker Simulation

Topology sets the quantity: distributed or central?

A common error in cable estimates

Assuming at feasibility stage that every string runs to a single central point overstates the DC quantity several times over for a distributed design, and overstates the voltage drop with it. Our simulator clusters the tables, places inverters at the cluster centres and inverters into transformer blocks, then measures cables along orthogonal routes following rows and roads. The cable quantities in the BOM and the voltage drop are therefore based on the actual site layout.

Practical checklist

Frequently asked questions

What is the maximum DC voltage drop in a PV plant?

There is no single binding limit; many EPCs target about 1–1.5% on the DC side and treat 3% as an upper bound. The right target comes from comparing cable cost with the energy lost over the project lifetime.

Which DC cable is used in tracker PV plants?

EN 50618 H1Z2Z2-K solar cable is common in 1500 V systems: 4–6 mm² for string cables and larger cross-sections for feeders in central-inverter designs.

Is a larger cable cross-section always better?

No. With long string cables, moving the inverter closer to the table group is often cheaper and more efficient than increasing the cross-section.

Turnkey solar tracker PV plants with BTR Enerji
We deliver the whole project: feasibility, engineering, procurement, installation and grid connection, in Türkiye and abroad. Simulate your site for free first, then let our team prepare a tailored quote.